The grant money is aimed to improve pedestrian safety and minimize crash potential by implementing countermeasures at the crossings on local urban roads and streets.
Installation/replacement of pedestrian signals, curb ramps, striping at the following intersections:

  1. Intersection of Washington Avenue, Forbes Avenue and 7th Street
  2. Intersection of Broadway and Partition Street
  3. Intersection of Broadway and Pine Street
  4. Intersection of Broadway and McNaughton Avenue
  5. Intersection of 1st Street, Partition Street and East Street
  6. Intersection of 3rd Street and Catherine Street.

Preliminary Plan Available Here:   1760.94_DDR Planset
Draft Design Report Available Here:  1760.94_Draft Design Report (combined)
Construction to begin during the Summer of 2020
Comments can be sent to Charles.moore@rensselaerny.gov or jgentzler@gpinet.com by September 23rd.